Henan Daswell Machinery Co., Ltd,is a professional manufacturer and trader specializing in the research, development and production of construction machinery for nearly 30 years. Our main products are as follows:concrete batch mix plant,diesel concrete mixer,portable cement mixers for sale,etc. We will provide you with the best product and service.
Cement silomiddle tube's disassembly concrete mixing plant, cement tank upper section's disassembly(including the roof), cement tank remove the feeding tube and how to install the cement tank.
First, remove the lower section of the tube body.
Slow after lifting rope on the crane hook up hook and a tight rope,
The funnel in the operation platform, and connect the bottom section of the tube body and the funnel bolts disassembly,
Then slowly up the hook DMP mixer planetary, after the separation section of the tube body and the funnel to be positioned and the lower section of the tube body to the ground.
Second, take apart the funnel.
1, the funnel hanging down the whole.the surface should be removed first before funnel.Operation platform, and then the lower part of funnel and screw conveyor of the connecting pipe, the tubes and the valve.Remove the separatory funnel and screw conveyor.Check the screw conveyor should be taken before separation. Stability, to dismantle the valve more weight before, such as applications are removed in hand gourd taut From, and then loosen the hoist it down.Article 26 mm diameter 4 wire rope hang on funnel plate corners mobile cement mixer,Hook hoist funnel again slowly, at the bottom of the funnel is higher than after the ring beam off shoring funnel to the ground.
2, funnel decomposition.After funnel landing, you should use 25 tons crane to take apart it, lift the bottom of the funnel after making the big end down on the ground and slightly tight rope, tear open
In addition to all the bottom connecting screws, separate the two layers on the lift to the bottom.Then the two Separation layer down to the ground, will also be returned to the upper floor after separation.Finally decomposition have separate three layers funnel into four conical roof tiles.Funnel layers into tiles, should reinforce the finally removed tiles in case within the tiles to overthrow, decomposition, can be in the two bent pipe inside welding pipe support,Inspection qualified after the decomposition, decomposition should be forbidden anyone into tiles capsized.